Essential Primavera P6 Tips Every Planner Should Use: Open Ends, Exporting to Excel, Fill Down, Single-Page Width, and Longest Path vs Total Float
- Mehmet Durak
- 29 Kas
- 2 dakikada okunur
In modern construction projects, time is one of the most valuable resources — and precise scheduling is the foundation of project success. Primavera P6 remains the industry standard for building logic-driven programmes, performing critical path analysis, and ensuring stakeholders understand the true status of a project.
Yet even experienced planners overlook simple but powerful features that can dramatically improve schedule quality, reporting clarity, and team communication.
In this article, we explore five essential Primavera P6 techniques:finding open ends, exporting schedules to Excel, using Fill Down, scaling schedules to single-page width, and understanding Longest Path vs Total Float.
Whether you’re a planner, project controls specialist, consultant, or contractor, these tips will help you deliver cleaner, more accurate, and more defensible schedules.
1. Finding Open Ends in the Activity Network: The First Step to a Reliable Schedule
Open ends — activities without predecessors or successors — are one of the most common causes of weak schedule logic. They create floating islands in your programme, distort the critical path, and make forecasting unreliable.
Why Open Ends Matter
A schedule with open ends can:
Artificially inflate float
Hide true criticality
Misrepresent sequencing
Lead to disputes over delays
Undermine the baseline
These issues can cost contractors both time and money — and make a schedule unacceptable to clients, funders, and auditors.
How to Identify Open Ends in P6
Primavera P6 offers several methods:
Use the Schedule Log (shows activities without predecessors or successors)
Create a Filter for:
Predecessors IS EMPTY
Successors IS EMPTY
Use the Network Diagram view to visually catch unlinked tasks
Run a Schedule Diagnostic Check before baseline submission
Best Practice
Every schedule should be free of open ends except for:
Project start
Project finish
Key externally driven milestones
Everything else must be logically connected.