Essential Primavera P6 Tips Every Planner Should Use: Open Ends, Exporting to Excel, Fill Down, Single-Page Width, and Longest Path vs Total Float

  • Mehmet Durak
  • 29 Kas
  • 2 dakikada okunur

In modern construction projects, time is one of the most valuable resources — and precise scheduling is the foundation of project success. Primavera P6 remains the industry standard for building logic-driven programmes, performing critical path analysis, and ensuring stakeholders understand the true status of a project.


Yet even experienced planners overlook simple but powerful features that can dramatically improve schedule quality, reporting clarity, and team communication.


In this article, we explore five essential Primavera P6 techniques:finding open ends, exporting schedules to Excel, using Fill Down, scaling schedules to single-page width, and understanding Longest Path vs Total Float.

Whether you’re a planner, project controls specialist, consultant, or contractor, these tips will help you deliver cleaner, more accurate, and more defensible schedules.


1. Finding Open Ends in the Activity Network: The First Step to a Reliable Schedule


Open ends — activities without predecessors or successors — are one of the most common causes of weak schedule logic. They create floating islands in your programme, distort the critical path, and make forecasting unreliable.


Why Open Ends Matter

A schedule with open ends can:

  • Artificially inflate float

  • Hide true criticality

  • Misrepresent sequencing

  • Lead to disputes over delays

  • Undermine the baseline

These issues can cost contractors both time and money — and make a schedule unacceptable to clients, funders, and auditors.


How to Identify Open Ends in P6

Primavera P6 offers several methods:

  • Use the Schedule Log (shows activities without predecessors or successors)

  • Create a Filter for:

    • Predecessors IS EMPTY

    • Successors IS EMPTY

  • Use the Network Diagram view to visually catch unlinked tasks

  • Run a Schedule Diagnostic Check before baseline submission


Best Practice

Every schedule should be free of open ends except for:

  • Project start

  • Project finish

  • Key externally driven milestones

Everything else must be logically connected.

 
 