Longest Path vs Total Float ≤ 0: Understanding True Criticality

  • Mehmet Durak
  • 29 Kas
  • 1 dakikada okunur

Critical path analysis is at the heart of planning — but not all planners fully understand the difference between Longest Path and Total Float ≤ 0 in Primavera P6.


Total Float ≤ 0

  • Shows activities with no float or negative float

  • Useful for identifying schedule compression

  • Helps locate contractual delivery pressure points

However, it can mislead when calendars vary or constraints distort float.


Longest Path

  • Tracks the actual driving sequence of activities leading to project completion

  • Ignores float distortions

  • More accurate for identifying true critical activities

  • Preferred by forensic schedulers and claims professionals


When to Use Each

Purpose

Best Method

True critical path?

Longest Path

Contractual float reporting?

Total Float ≤ 0

Delay analysis?

Longest Path + change tracking

Executive reporting?

Longest Path

Understanding this difference is essential for producing defensible, dispute-proof schedules.

 
 